Which project management methodology involves creating a clear sequence of project stages?

Prepare for the ServiceNow IT Leadership Professional Exam with our comprehensive quiz. Gain confidence with flashcards and multiple choice questions, featuring helpful hints and explanations. Ensure your success!

The correct answer is Critical Path Analysis, which is a project management methodology that focuses on identifying the longest sequence of dependent tasks to determine the minimum project duration. This technique helps project managers outline a clear sequence of project stages by identifying essential tasks, their durations, and their dependencies. By doing so, it allows for effective scheduling and resource allocation, ensuring that necessary tasks are completed sequentially and efficiently.

Methods like PRINCE2 and Waterfall do also emphasize structured project phases, but Critical Path Analysis uniquely provides a visual and analytical method for determining the critical sequence of activities and their timing. While Agile promotes flexibility and iterative progress without a strict linear project stage sequence, it does not fit the description of creating a clear sequence of stages as directly as Critical Path Analysis does.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy